Miami World Towers Construction Update
Miami World Tower 1
WEEK OF 06/05/2023 – 06/09/2023:
Forming and Pouring on Levels 46 & 47
CMU Block Installation on Levels 40
Interior Drywall Framing for Level 30-33
Window Installation at Level 37
Stucco at Balconies at Level 33
WEEK OF 06/12/2023 – 06/16/2023:
Forming and Pouring on Levels 48
CMU Block Installation on Levels 41
Interior Drywall Framing for Level 31-34
Window Installation at Level 38 & 39
Stucco at Balconies at Level 34 & 35
WEEK OF 06/19/2023 – 06/23/2023:
Forming and Pouring on Levels 49 & 50
CMU Block Installation on Levels 42 & 43
Interior Drywall Framing for Level 32-35
Window Installation at Level 40
Stucco at Balconies at Level 36
WEEK OF 06/26/2023 – 06/30/2023:
Forming and Pouring on Levels 50 & 51
CMU Block Installation on Levels 44
Interior Drywall Framing for Level 33-36
Window Installation at Level 41
Stucco at Balconies at Level 37
Miami World Tower 2
Coming Soon
Miami World Tower 3
Coming Soon