Miami World Towers Construction Update

Miami World Tower 1

 WEEK OF 06/05/2023 – 06/09/2023:

  • Forming and Pouring on Levels 46 & 47

  • CMU Block Installation on Levels 40

  • Interior Drywall Framing for Level 30-33

  • Window Installation at Level 37

  • Stucco at Balconies at Level 33

 

WEEK OF 06/12/2023 – 06/16/2023:

  • Forming and Pouring on Levels 48

  • CMU Block Installation on Levels 41

  • Interior Drywall Framing for Level 31-34

  • Window Installation at Level 38 & 39

  • Stucco at Balconies at Level 34 & 35

 

WEEK OF 06/19/2023 – 06/23/2023:

  • Forming and Pouring on Levels 49 & 50

  • CMU Block Installation on Levels 42 & 43

  • Interior Drywall Framing for Level 32-35

  • Window Installation at Level 40

  • Stucco at Balconies at Level 36

 

WEEK OF 06/26/2023 – 06/30/2023:

  • Forming and Pouring on Levels 50 & 51

  • CMU Block Installation on Levels 44

  • Interior Drywall Framing for Level 33-36

  • Window Installation at Level 41

  • Stucco at Balconies at Level 37

Miami World Tower 2

Coming Soon

Miami World Tower 3

Coming Soon